| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | ENG | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | TM | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:10 | N 7996 UE | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | ENG | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | TM | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | ENG | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | TM | RFU - READY FOR USE Baru Saja |
singgih.fonda |
|
| 06 Feb 2026 | 08:09 | N 7996 UE | UPDATE | ENG | RFU - READY FOR USE 3 Hari 21 Jam 47 Menit |
singgih.fonda |
|
| 06 Feb 2026 | 08:08 | N 7996 UE | MOVE IN | UNIT | WAITING LINE OCCUPIED 2 Hari 22 Jam 33 Menit |
Masuk ke FINISHING |
singgih.fonda |
| 05 Feb 2026 | 15:43 | N 7658 UE | UPDATE | ENG | B0 - ON PROGRESS 5 Hari 1 Jam |
Install Front 4 x 2 & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:43 | N 7658 UE | UPDATE | TM | B0 - ON PROGRESS Baru Saja |
Install Front 4 x 2 & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:43 | N 7658 UE | UPDATE | AXL | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Install Front 4 x 2 & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:43 | N 7658 UE | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
Install Front 4 x 2 & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:43 | N 7658 UE | UPDATE | WTR | RFU - READY FOR USE B0 - ON PROGRESS Baru Saja |
Install Front 4 x 2 & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | ENG | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | TM | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | WTR | RFU - READY FOR USE B0 - ON PROGRESS Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | ENG | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | TM | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:42 | N 7349 UI | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
Rebuild Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | ENG | RFU - READY FOR USE 5 Hari 55 Menit |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | TM | RFU - READY FOR USE Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | WTR | RFU - READY FOR USE B0 - ON PROGRESS Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | ENG | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | TM | RFU - READY FOR USE B0 - ON PROGRESS Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:41 | N 7349 UI | UPDATE | AXL | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Install Transmission Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:40 | BG 696 | UPDATE | TM | B0 - ON PROGRESS RFU - READY FOR USE 1 Hari 1 Jam 6 Menit |
Install Tyre Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:40 | BG 696 | UPDATE | AXL | RFU - READY FOR USE Baru Saja |
Install Tyre Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:40 | BG 696 | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
Install Tyre Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:40 | BG 696 | UPDATE | WTR | RFU - READY FOR USE Baru Saja |
Install Tyre Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:39 | BG 688 | UPDATE | TM | B0 - ON PROGRESS 4 Jam 29 Menit |
Install Front Axle & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:39 | BG 688 | UPDATE | AXL | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Install Front Axle & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:39 | BG 688 | UPDATE | SUS | RFU - READY FOR USE Baru Saja |
Install Front Axle & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:39 | BG 688 | UPDATE | WTR | RFU - READY FOR USE B0 - ON PROGRESS Baru Saja |
Install Front Axle & Differential Ready |
prisandi.achmad |
| 05 Feb 2026 | 15:20 | KT 7201 GU | UPDATE | TM | B0 - ON PROGRESS 1 Menit |
Washing |
muharlin.syarif |
| 05 Feb 2026 | 15:20 | KT 7201 GU | UPDATE | AXL | B0 - ON PROGRESS Baru Saja |
Washing |
muharlin.syarif |
| 05 Feb 2026 | 15:20 | KT 7201 GU | UPDATE | SUS | B0 - ON PROGRESS Baru Saja |
Washing |
muharlin.syarif |
| 05 Feb 2026 | 15:20 | KT 7201 GU | UPDATE | WTR | B0 - ON PROGRESS Baru Saja |
Washing |
muharlin.syarif |
| 05 Feb 2026 | 15:20 | KT 7201 GU | UPDATE | ENG | B0 - ON PROGRESS RFU - READY FOR USE Baru Saja |
Washing |
muharlin.syarif |
| 05 Feb 2026 | 15:18 | KT 7201 GU | UPDATE | ENG | B0 - ON PROGRESS 5 Jam 36 Menit |
Proses Washing |
muharlin.syarif |
| 05 Feb 2026 | 13:18 | N 7093 UF | MOVE IN | UNIT | WAITING LINE OCCUPIED 3 Menit |
Masuk ke INSPECTION |
singgih.fonda |