Pencarian Detail Unit
Detail Unit: N 7039 UH (Progress: 40%)
Identitas Unit
Unit ID (System) 307
Plat Nomor N 7039 UH
Product Code -
Kondisi Recondition
Spesifikasi
Model -
Tipe -
Axle -
Tahun -
Lokasi & Status
Area Saat Ini FINISHING (F2)
Site -
Client -
Referensi
No SPK -
Purchase Code -
Karoseri -
Status Pengerjaan Komponen
Prog. Periksa Mesin (PPM)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
Wheel Tyre Rim (WTR)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
Suspension (SUS) RFU
Status RFU - READY FOR USE
PIC Didik Pur
Mulai - -
Selesai 2026-09-23 15:39:00
Durasi -
Engine (Install) RFU
Status RFU - READY FOR USE
PIC Didik Pur
Mulai - -
Selesai 2026-09-23 15:30:00
Durasi -
Transmission (Install) RFU
Status RFU - READY FOR USE
PIC Didik Pur
Mulai - -
Selesai 2026-09-23 15:38:00
Durasi -
Axle (Install) RFU
Status RFU - READY FOR USE
PIC Didik Pur
Mulai - -
Selesai 2026-09-23 15:39:00
Durasi -
Electrical (ELC)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
Air Conditioner (ACD) PROG
Status B1 - WAITING PARTS
PIC ridwan
Mulai 2026-09-28 10:23:00
Selesai - -
Durasi -
Main Frame Chasis (MFC)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
Accessories (ACC) PROG
Status B0 - ON PROGRESS
PIC Gosong
Mulai 2026-09-28 10:23:00
Selesai - -
Durasi -
Final Check (FNC)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
Painting (PNT)
Status -
PIC -
Mulai - -
Selesai - -
Durasi -
REBUILD - Engine RFU
Status RFU - READY FOR USE
PIC Wibisono
Mulai 2026-09-12 08:30:00
Selesai 2026-09-21 10:42:00
Durasi 9 Hari 2 Jam
REBUILD - Transmission RFU
Status RFU - READY FOR USE
PIC Suhendro
Mulai 2026-09-18 10:49:00
Selesai 2026-09-21 10:49:00
Durasi 3 Hari
REBUILD - Axle PROG
Status B0 - ON PROGRESS
PIC Alfian
Mulai 2026-09-19 14:00:00
Selesai - -
Durasi -